In-Process Inspection
If the production run consists of more than 50 parts,
an in-process inspection will be performed at a rate designated by Quality
Control. The inspection will be based on the complexity and tolerance of
the part.
This inspection shall be noted on the reverse side
of the Manufacturing Operations Sheet. All in-process inspections will be
so noted. The information required is as follows:
CRITERIA
PIECE #
ACC/REJ
DATE
BY
The inspected parts will be identified as acceptable
or unacceptable so that no co-mingle will occur in the production run.
If a reject is found during an in-process inspection,
the lot will be 100% inspected for that criteria and the parts rejected
will be segregated and identified as non-conforming material.
This must be so noted on the reverse side of the
Manufacturing Operations Sheet and the foreman notified immediately.
|